• We has been entrusted by Gas Processing & Utilities (GPU) as the Main Mechanical Package Contractor for Utilities Kertih Demin(UK) Plant Turnaround 2019. MMSSB has been awarded to execute the main mechanical packages and associated works for the GPP-3 & FGRU Plant Turnaround which was started to performed in March until April 2019.

  • Turnaround packages for Demin Phase 1 Turnaround 2019 was started with plant shutdown on 17th March 2019 where the UK operation and Mushtari operation-support team utilized whole day with shutdown activities. Then, mechanical day was declared on 18th March 2019 at 0800hrs for a period of 26 days. MMSSB were completed within 26 days instead of planned 29 days of mechanical days commenced on 18th March 2019 till 12th April 2019 including all additional LWRAS (Late Work Additional Request) activity.

  • The progress from main package contractor truly affected the overall S-curve for Demin Phase 1 Turnaround 2019. The good achievement from MMSSB and other main package contractors has been shown in the overall S-Curve. Total worklist for main mechanical package 47 nos static equipment.

  • Total man-hours achieved during turnaround started from Shutdown Day, 17th March 2019 until Plant Start-Up, 13th April 2019 were 214,530 man-hours with zero incident or accident recorded during this Turnaround 2019.

  • The progress from main package contractor truly affected the overall S-curve for Demin Phase 1 Turnaround 2019. The good achievement from MMSSB and other main package contractors has been shown in the overall S-Curve. Total worklist for main mechanical package 47 nos static equipment.

  • MMSSB has appointed 2 QC Supervisor and 2 JIT Coordinator which undergo for qualification training by PGB to ensure all the QC/JIT Supervisor understood and implement the JIT procedures.

  • MMSSB also has trained a total more than 115 pax of Joint Maker to check, identify and report all of the
    joints opened during turnaround. Total Registered Joints is 384 nos Joints.

  • Defect notification make up significant portion of the overall Demin Phase 1 Turnaround 2019 work list. Being the main package contractor, MMSSB has been entrusted to execute majority of the work. Total defect 453 nos. All defects were found during the inspection of the equipment.